Stage One Complete!
October 3rd, 2008
Despite consistently poor weather conditions, the first of five reef sections has now been laid, filled and completed. ASR are continuing to work on the deployment and filling of bags in the base layer of the reef.
Due to adverse weather, the placing and filling strategy has been changed so that the second reef section has been divided into two sections. This is more manageable than deploying one large section in short weather windows. All the bags have been folded and loaded onto the placement barge, ready for the next good weather window.
The next regular surf reef review meeting is planned for 10 October. We’ll be coming back to you with an update after this date.

![[del.icio.us]](http://www.bournemouthsurfreef.com/wp-content/plugins/bookmarkify/delicious.png)
![[Digg]](http://www.bournemouthsurfreef.com/wp-content/plugins/bookmarkify/digg.png)
![[Facebook]](http://www.bournemouthsurfreef.com/wp-content/plugins/bookmarkify/facebook.png)
![[Google]](http://www.bournemouthsurfreef.com/wp-content/plugins/bookmarkify/google.png)
![[MySpace]](http://www.bournemouthsurfreef.com/wp-content/plugins/bookmarkify/myspace.png)
![[Newsvine]](http://www.bournemouthsurfreef.com/wp-content/plugins/bookmarkify/newsvine.png)
![[Reddit]](http://www.bournemouthsurfreef.com/wp-content/plugins/bookmarkify/reddit.png)
![[StumbleUpon]](http://www.bournemouthsurfreef.com/wp-content/plugins/bookmarkify/stumbleupon.png)
![[Technorati]](http://www.bournemouthsurfreef.com/wp-content/plugins/bookmarkify/technorati.png)
![[Twitter]](http://www.bournemouthsurfreef.com/wp-content/plugins/bookmarkify/twitter.png)
![[Windows Live]](http://www.bournemouthsurfreef.com/wp-content/plugins/bookmarkify/windowslive.png)
![[Yahoo!]](http://www.bournemouthsurfreef.com/wp-content/plugins/bookmarkify/yahoo.png)






Leave a comment